Rehabilitation of static, dynamic equipment, instrumentation, electrical equipment, civil works, process lines, supply of materials and spare parts.
Placement of J / C, equipment disassembly (reel disassembly, flat cover, bonnet, back cover and floating cover).

  • Extraction of tube bundle (with extractor), cleaning inside and outside.
  • Arm (reel assembly, flat lid, bonnet, back cover and floating lid) and hydrostatic tests.
  • Return and placement of thermal insulation.
  • Installation of stump type support in 48 “pipe.
  • Construction of armed stew with a weight of 20 tons. in its base for integration.
  •  Assembly of coils in the bottom of the sulfur pit.
  • Place of J / C, disarmed of equipment (disassembly of reel, flat cover, bonnet, back cover and floating cover).
  • Extraction of tube bundle (with extractor), cleaning inside and outside.
  • Arm (reel assembly, flat cap, bonnet, back cover and lid floating) and hydrostatic testing.
  • Rehabilitation of sulfur pit.
  • Removal of solid sediments, inside the pit, replacement of the coils of the coil and hydrostatic tests.